NEWS

Buyers cannot be made to wait indefinitely for possession of property, says NCDRC


MAY 23, 2019

Buyers cannot be made to wait indefinitely for possession of their properties, under the pretext of the force majeure clause, the apex consumer court has said

The National Consumer Disputes Redressal Commission (NCDRC) has said that housing developers’ action of relying on the clause of force majeure, while retaining the amounts deposited by complainant, is not only an act of deficiency of service but also of unfair trade practice. The apex consumer court made the observation while directing a Gurugram-based developer to refund over Rs 1.15 crores to a man, for not delivering his flat on time. Force majeure is a contract provision which relieves parties from performing contractual obligations if unforeseeable circumstances beyond their control arise.

“We are of the view that the complainant cannot be made to wait indefinitely, for the delivery of possession and the act of the opposite party (developer) in relying on Force Majeure clause, while retaining the amounts deposited by the complainant, is not only an act of deficiency of service but also of unfair trade practice,” the commission’s bench comprising president RK Agrawal and member M Shreesha said.

The bench passed the order while allowing a complaint filed by Ashok Kumar Taneja, who had booked an apartment with Orris Infrastructure Private Limited in Gurugram and paid over Rs 1.15 crores, from May 2012 to December 2016. According to the complainant, the developer had promised to hand over the possession of the apartment in December 2015. He said more than 7 years had lapsed from the date of agreement but he had not got the property.

The bench also held as ‘extremely unfair’ and ‘one-sided’, the force majeure clause along with others, such as the developer charging interest at 18% for any delay in payments made by flat purchasers, but at the same time if the project is abandoned, refund would be made at an interest of 9% only. The commission allowed Taneja’s plea and directed the developer to refund the principal amount, that is, over Rs 1.15 crores, with interest at 12% per annum. It also directed the developer to pay litigation cost of Rs 25,000 to Taneja. “The complainant cannot be made to wait indefinitely for possession of the unit, as the construction is yet to be completed even after a period of more than 7 years from the date of agreement. Therefore, we are of the considered view that the complainant is entitled for refund of the principal amount, with reasonable interest,” said the Commission.

The counsel appearing for the developer submitted that the time given for completion of the project before the RERA was June 30, 2020 and it would be completed, as on that date. However, Taneja’s counsel said that he was not willing to wait till June 30, 2020, for taking possession, as the promised date of delivery of possession was way back in December 2015.



Share This:



Read all Thane Real Estate Latest News


 

To Know About Thane Real Estate Development Contact Us at 022 2580 6868


Source: housing.com